Framingham Generator Installation
Ahearn Holtzman Inc. successfully replaced an aging 3rd-floor turbine generator with a 2-megawatt emergency backup reciprocating diesel generator, ensuring reliable power continuity for this critical facility.
Framingham Generator Installation
Ahearn Holtzman Inc. successfully replaced an aging 3rd-floor turbine generator with a 2-megawatt emergency backup reciprocating diesel generator, ensuring reliable power continuity for this critical facility.















Framingham Generator Installation
Ahearn Holtzman Inc. successfully replaced an aging 3rd-floor turbine generator with a 2-megawatt emergency backup reciprocating diesel generator, ensuring reliable power continuity for this critical facility.















Overview of Project
- Square Footage : N/A
- Address : Framingham, MA
The project featured:
-
Generator Replacement: Installed a modern 2MW diesel generator to enhance backup power capacity.
-
EPA-Compliant Exhaust System: Added a new 24-inch insulated stainless steel stack extending above the roofline.
-
Structural Enhancements: Reinforced building structure to support generator and stack installation.
-
Air & Sound Systems: Integrated new louvers, dampers, sound attenuation devices, and ductwork for combustion and cooling.
-
Fuel & Control Upgrades: Updated fuel oil controls, alarms, and generator automation for seamless power transfers.
-
Portable Generator Integration: Installed a new connection box for temporary generator use during maintenance.
All work was completed without interrupting ongoing telecommunications operations, maintaining normal plus-one power throughout via utility service and a portable generator.
This project underscores Ahearn Holtzman’s ability to deliver mission-critical infrastructure upgrades with precision, safety, and zero downtime.